Hostel for «Kazenergoinvest» LLP

previous arrow
next arrow
previous arrownext arrow
Slider
  • Customer:

    «Kazenergoinvest» LLP

  • Implementation dates:

    October-November 2015.

  • Total area:

    306.8 m²

In mid-November 2015, a hostel for builders of «Kazenergoinvest» LLP from sunny Kazakhstan was put into operation

Before us was the task of organizing comfortable living for 64 workers at a construction site in the middle of the steppe — build a 2-levels hostelusing modular technology in 2 months

When implementing this project, our company’s specialists provided a full range of services:

1

 

Development of project documentation within 15 days (architectural solutions, metal structures; water supply and sewerage system; heating and ventilation system;electric power equipment and lighting).

Explication of modular canteen premises:

— living rooms for 64 people;

— Bathroom units and showers.

2

Production of modular and metal structures in 30 days

3

 

Car delivery to Zhibek Zholy, Akmola region in 2 days on 5 eighteen-wheelers

4

 

Installation works were done by our company in 25 days

5

DL specialists of «Avista Module Engineering» supplied withshowersand bathroom units.